Discount irregular dated cash flows on a 365-day basis

Discount cash flows arriving on exact irregular calendar dates using SUM(CashFlows / ((1 + Rate) ^ ((Dates - StartDate) / 365))).

Use elapsed days for irregular cash-flow timing

NPV uses equally spaced periods and a discount rate per period; those periods are not necessarily years. Its first supplied cash flow is discounted by one period. This example instead discounts from the date in A2.

For valid whole-day dates and an annual rate greater than -100%, SUM(B2:B5/((1+D2)^((A2:A5-A2)/365))) applies the 365-day convention used by XNPV. The initial outlay is included at day zero. Round the total, rather than each intermediate present value.

Use matching numeric cash-flow and date ranges, with A2 as the earliest date. This algebraic expression does not reproduce all XNPV input-validation behavior. It is a valuation example, not an investment recommendation; the appropriate discount rate depends on the application.

Cash Flow Date (A)Elapsed DaysCash Flow (B)PV @ 10% Discount Rate
2026-01-01 (Close)0 days-$10,000-$10,000.00
2026-04-0190 days+$3,000+$2,930.15
2026-10-01273 days+$4,500+$4,190.54
2027-01-01365 days+$4,000+$3,636.36 (XNPV = +$757.06)

Dated present-value sum, rounded to cents

Array subtraction (A2:A5 - A2) / 365 discounts every row back to the initial closing date A2.

=IF(D2<=-1,"Rate must exceed -100%",ROUND(SUM(B2:B5 / ((1 + D2) ^ ((A2:A5 - A2) / 365))), 2))

Undiscounted net cash flow

At D2 = 0%, daily-discounted NPV collapses cleanly to SUM(B2:B5).

=SUM(B2:B5)