Project midpoint date and % schedule time elapsed (calendar vs workdays)

Find a calendar-date midpoint and an inclusive workday schedule ratio.

Calendar halfway date vs Business-Day halfway date

Start+INT((End-Start)/2) selects the earlier calendar date when the exact midpoint falls at noon.

The workday ratio below counts the status date inclusively and clamps the result to the interval 0–1.

Project Metric (2026-06-01 Mon to 2026-06-19 Fri)FormulaResult
Calendar Span=B2 - A218 calendar days
Calendar Midpoint Date=A2 + INT((B2 - A2) / 2)2026-06-10 (Day 10)
Total Business Days=NETWORKDAYS(A2, B2)15 workdays
% Time Burn as of 2026-06-05 Fri=NETWORKDAYS(A2, C2) / 1533.33% (5 of 15 workdays)

Calendar-date midpoint

INT((End - Start) / 2) keeps the midpoint date a pure integer serial with no 12:00 PM half-day timestamp.

=TEXT(A2+INT((B2-A2)/2),"yyyy-mm-dd")

Clamped % business days elapsed as of status date C2 (0% to 100%)

If StatusDate precedes StartDate, return 0; otherwise clamp completed workdays / total workdays at 1.00 (100%).

=IF(OR(B2<A2,NETWORKDAYS(A2,B2)<=0),"No valid workday span",ROUND(IF(C2 < A2, 0, MIN(1, NETWORKDAYS(A2, C2) / NETWORKDAYS(A2, B2))), 4))

Inputs and interpretation

The calendar formula floors a half-day midpoint to the earlier calendar date. The elapsed-workday ratio includes the status date as a whole day; it is not intraday elapsed time or work completed. This example uses Monday–Friday and no holidays. A holiday-aware business midpoint must use the same holiday list in WORKDAY and NETWORKDAYS and a valid working-day anchor.

Try the example

Use the original values or change them to test your understanding.