PERT three-point estimates and a fixed path’s duration uncertainty

Convert Optimistic, Most Likely, and Pessimistic estimates into PERT Weighted Mean (O + 4M + P)/6, Task SD (P - O)/6, and Quadrature Path Risk.

Distinguish an estimate from a simulated project schedule

The conventional PERT weighted estimate is (O+4M+P)/6 and its standard-deviation heuristic is (P-O)/6. These are modeling approximations based on ordered estimates O<=M<=P, not measured guarantees or the exact variance of every beta distribution.

For independent sequential task durations on a fixed path, variances add. Task standard deviations of 3 and 4 give path SD sqrt(9+16)=5. Correlated tasks also require covariance terms.

This example neither runs Monte Carlo simulation nor finds a critical path. Multiple competing paths and dependencies can change the project completion distribution; normal probability bounds need additional assumptions.

PERT Risk FormulaCalculationResult
PERT Expected Duration (6, 10, 20)=(6 + 4*10 + 20) / 611.00 days
Single-Task PERT SD=(20 - 6) / 62.3333 days
Critical Path SD (Task SDs 3d & 4d)=SQRT(SUM({3;4}^2))5.00 days under independence

PERT 3-point expected value and Critical Path SD formulas

Weights Optimistic (1/6), Most Likely (4/6), and Pessimistic (1/6).

=ROUND((A2 + 4 * B2 + C2) / 6, 4)

Combined Critical Path Standard Deviation across independent tasks

Root-sum-of-squares SQRT(SUM(E2:E3 ^ 2)) adds variances properly.

=ROUND(SQRT(SUM(E2:E3 ^ 2)), 4)

Single-task standard-deviation estimate

Use the same time unit for all three inputs.

=ROUND((C2-A2)/6,4)