Earned Value Management (EVM) formulas: EV, PV, CPI, SPI, and EAC

Distinguish true physical progress from raw budget burn using Cost Performance Index (CPI = EV / AC), Schedule Performance Index (SPI = EV / PV), and EAC.

Why comparing Actual Spend vs Planned Budget alone hides cost overruns!

At BAC=$200,000, planned budget-weighted progress 50% and earned progress 45%, PV=$100,000 and EV=$90,000. With AC=$100,000, both cost variance and schedule variance are -$10,000 in budget-value terms.

CPI and SPI are 0.90. EAC=BAC/CPI projects $222,222.22 only if the same cost efficiency continues.

EVM Metric (BAC = $200k, Plan 50%, Done 45%, AC = $100k)FormulaResult
Planned Value (PV) & Earned Value (EV)BAC*50% / BAC*45%$100,000 / $90,000
Cost Performance Index (CPI)=EV / AC = 90k / 100k0.90 (Over budget < 1.0)
Schedule Performance Index (SPI)=EV / PV = 90k / 100k0.90 (Behind schedule < 1.0)
Estimate at Completion (EAC)=BAC / CPI = 200k / 0.90$222,222.22

CPI, SPI, and Estimate at Completion (EAC) formulas

A ratio of 1 means performance matches the baseline; above or below 1 needs interpretation in the project context.

=ROUND((A2 * C2) / D2, 4)

Estimate at Completion (EAC = BAC / CPI)

Projects final total cost assuming remaining work continues at historical CPI efficiency.

=ROUND(A2 / ((A2 * C2) / D2), 2)

Additional worked calculation

Using the initial example inputs:

=ROUND((A2 * C2) / (A2 * B2), 4)

Inputs and interpretation

Earned value is budgeted value of completed work. Multiplying BAC by a completion percentage assumes that percentage is budget-weighted. Require positive BAC and actual cost; SPI needs positive planned value and EAC needs positive earned value. Cost and schedule variances are currency measures, not a forecast dollar overrun or number of days late. EAC= BAC/CPI assumes the same future cost efficiency.

Try the example

Use the original values or change them to test your understanding.