Drum-Buffer-Rope (DBR) Buffer Penetration % & TOC Green/Yellow/Red Expedite Priority

Calculate Theory of Constraints (TOC) time-buffer consumption percentage 100 * (Buffer_Hours - Remaining_Hours) / Buffer_Hours and classify work orders into Region I Green (<33.3%), Region II Yellow (33.3%–66.7%), or Region III Red (>66.7%) expedite zones.

Prioritize shop-floor expediting by TOC Buffer Penetration—not local machine efficiency!

In Eliyahu Goldratt's Theory of Constraints (TOC) Drum-Buffer-Rope (DBR) scheduling, the Drum (system bottleneck) sets the master schedule, the Rope gates raw-material release exactly Buffer_Hours ahead of the Drum (or customer ship date), and the Time Buffer absorbs Murphy's Law upstream disruptions so the Drum never starves!

Buffer Management replaces chaotic due-date firefighting with a single metric—Buffer Penetration % = 100 * (Buffer_Hours - Remaining_Hours_to_Due) / Buffer_Hours! Dividing a 24-hour constraint buffer into three equal 1/3 zones: Region I Green (< 33.3% consumed, >= 16 hr remaining) means hands-off normal flow; Region II Yellow (33.3% to 66.7% consumed) triggers upstream tracking/watch; and Region III Red (> 66.7% consumed, e.g., only 6 hr left on an unarrived order -> 75.0% penetration!) triggers immediate shop-floor expediting!

Work Order (24 hr Constraint Buffer)Hours Remaining to DrumBuffer Penetration %TOC Buffer Management Zone
WO-101 (Upstream Smooth)18 hr remaining25.0% consumedGreen Zone (<33.3%: Do Not Expedite)
WO-102 (Delayed at Prep)12 hr remaining50.0% consumedYellow Zone (33.3%-66.7%: Locate & Watch)
WO-103 (Machine Breakdown)6 hr remaining75.0% consumedRed Zone (>66.7%: Expedite Immediately!)
WO-104 (Past Drum Schedule!)-3 hr remaining112.5% consumedBlack / Late (>100%: Buffer Exhausted!)

TOC Time-Buffer Penetration Percentage (%)

Computes 100 * (Total_Buffer_Hours - Remaining_Hours) / Total_Buffer_Hours for positive buffer B2.

=IF(B2 <= 0, "Invalid Buffer Size", ROUND(100 * (B2 - B3) / B2, 1))

Three-Zone TOC Buffer Management Priority Status

Classifies buffer penetration into Green (<= 1/3), Yellow (<= 2/3), Red (<= 100%), or Late (> 100%).

=IF(B2 <= 0, "Invalid Buffer Size", IF(((B2 - B3) / B2) > 1, "Black Zone (>100%: Late!)", IF(((B2 - B3) / B2) > (2 / 3), "Red Zone (>66.7%: Expedite!)", IF(((B2 - B3) / B2) > (1 / 3), "Yellow Zone (Watch)", "Green Zone (On Track)"))))

Try the example

Use the original values or change them to test your understanding.

Further reading