Add Workdays on a 6-Day (Mon–Sat) Custom Workweek (Skipping Sundays)

Calculate exact delivery, construction, or retail SLA deadlines on a 6-day Monday–Saturday schedule (skipping Sundays only) using universal closed-form weekday arithmetic A2 + B2 + INT((MOD(WEEKDAY(A2, 2), 7) + B2 - 1) / 6).

Schedule 6-day Mon–Sat delivery and construction SLAs accurately!

Standard WORKDAY(start_date, days) hardcodes a 5-day Monday–Friday office week—skipping BOTH Saturday and Sunday! Yet parcel carriers, construction crews, manufacturing plants, and retail clinics frequently operate a 6-day Monday–Saturday workweek where Saturday IS a working day and ONLY Sunday is closed!

You can compute exact Monday–Saturday workday deadlines in closed form across EVERY spreadsheet engine using WEEKDAY(Start, 2) (where Monday = 1 .. Saturday = 6, Sunday = 7): wrapping MOD(WEEKDAY(B2, 2), 7) maps Monday..Saturday to 1..6 and Sunday to 0, so INT((MOD(WEEKDAY(B2, 2), 7) + C2 - 1) / 6) counts the exact number of Sundays crossed when advancing C2 >= 1 working days! Adding +5 Mon–Sat workdays to Friday 2026-10-30 works Saturday Oct 31 (Day 1), skips Sunday Nov 1, and works Mon–Thu to finish on Thursday 2026-11-05!

Start Date (B2)Mon–Sat Workdays Added (C2)Sundays CrossedCompletion Date
2026-10-30 (Friday)+5 workdays1 Sunday (Nov 1)2026-11-05 (Thursday)
2026-10-30 (Friday)+1 workday0 Sundays (Saturday counts!)2026-10-31 (Saturday)
2026-11-01 (Sunday)+6 workdaysStarts Mon Nov 2 -> Sat Nov 72026-11-07 (Saturday)

Add N >= 1 Mon–Sat Workdays (Skipping Sundays Only, ISO yyyy-mm-dd)

Adds C2 workdays plus INT((MOD(WEEKDAY(B2, 2), 7) + C2 - 1) / 6) crossed Sundays, returning B2 unchanged when C2 = 0.

=IF(C2 < 0, "Use Non-Negative Workdays", IF(C2 = 0, TEXT(B2, "yyyy-mm-dd"), TEXT(B2 + C2 + INT((MOD(WEEKDAY(B2, 2), 7) + C2 - 1) / 6), "yyyy-mm-dd")))

Number of Sundays Crossed During the 6-Day SLA Window

Isolates the exact count of non-working Sundays skipped between B2 and the completion date.

=IF(C2 <= 0, 0, INT((MOD(WEEKDAY(B2, 2), 7) + C2 - 1) / 6))